FK raised Part 8 court proceedings to challenge the validity of PA16.
They argued that for the payment application to be valid, it needed to have been received on or before the end of the site working hours on 20 October 2022 on the basis that if the application had been received some time on 21 October 2022, this would not be four days before 25 October 2022 but would instead be between three and four days.
In the alternative, FK argued that PA16 should have been received on or before the end of the site working hours on 21 October 2022.
Per the Sub-Contract specification, the site was to be open until 6 pm Monday-Friday and until 1 pm on Saturdays.
At the same time, Elements issued Part 7 proceedings to enforce the adjudicator's decision and apply for summary judgment against FK.
They also served evidence in response to the FK's Part 8 claim, which argued that Clause 4.6.3 of the Sub-Contract does not specify whether the notice needs to be served in 4 "clear" days or 4 "full" days.
They relied on the rule in English law that when interpreting contracts, a day is to be treated as an indivisible whole, and fractions of a day are ignored and that Sub-Contract did not specify any restrictions as to the time of day by which an application would be deemed validly served.
Elements also relied on the fact that previous applications had been received after working hours and that it was typical for members of the Quantity Surveying team and senior management to work long hours, including evenings and weekends, and receive emails during those times.